Correction-of-Error (COE) Template

  1. Title:
  2. Incident date:
  3. Owner:
  4. Peer-review committee:
  5. Tags:
  6. Summary:
  7. Supporting data:
  8. Customer Impact:
  9. Incident Response Analysis:
  10. Post-Incident Analysis:
  11. Timeline:
  12. Contributing factors:
  13. Lessons Learned:
  14. Action items:

1 - Title:

Descriptive title (Service XYZ failed, affecting customers in the EU region)

2 - Incident date:

Date of the event.

3 - Owner:

Name of the owner of the postmortem process.

4 - Peer-review committee:

List of people that will verify the quality of the postmortem before publishing it.

5 - Tags:

List of tags or keywords to classify the event and facilitate future search and analysis. Example: Configuration, Database, Dependency, Latent

6 - Summary:

A summary of the event.

7 - Supporting data:

Metric graphs, tables, or other data, that best illustrate the impact of this event.

8 - Customer Impact:

Discuss customer-impact during the event. Explicitly mention the number of impacted customers.

9 - Incident Response Analysis:

  • Example of questions you could address:
  • Was the event detected within the expected time?
  • How was it detected? (e.g., alarm, customer ticket)
  • How could time to detection be improved?
  • Did the escalation work appropriately?
  • Would earlier escalation have reduced or prevented the event?
  • How did you know how to mitigate the event?
  • How could time to mitigation be improved?
  • How did you confirm the event was entirely mitigated?

10 - Post-Incident Analysis:

  • Example of questions you could address:
  • How were the contributing factors diagnosed?
  • How could time to diagnosis be improved?
  • Did you have an actual backlog item that could’ve prevented or reduced the impact of this event? If yes, * why was this item not done?
  • Could a programmatic verification rule (e.g., AWS Config) be used to prevent this event?
  • Did a change trigger this event?
  • How was that change deployed — automatically or manually?
  • Could safeguards in the deployment have prevented or reduced the impact of this event?
  • Could this have been caught and rolled back during the deployment?
  • Was this tested in a staging environment? If yes, why did this pass through? Could more tests have * prevented or reduced the impact of this event?
  • If this change was manual, was there a playbook? Was that playbook practiced, tested, and reviewed recently?
  • Did a specific tool/command trigger the event? Could safeguards have prevented or reduced the impact of * this event? Was there any safeguard triggered? If not, why none were in place?
  • Was a production operation readiness or well-architected review performed on the system(s)? If not, why? * When was the last evaluation done?
  • Could a review have prevented or reduced the impact of the event?

11 - Timeline:

  • Detail all major event points with their time (included the timezone) with a short description.
  • Example: 09:19 EEST — database run out of connections. Link graph & log

12 - Diving deep on contributing factors:

  • Start with the problem.
  • Keep asking questions (e.g., why?) until you get to multiple contributing factors. There is no single cause * for failure. So, keeping going!
  • Probe into different directions — tools, culture, and processes.
  • NEVER stop at human errors (e.g., if an operator enters a wrong command, ask why no safeguards were in * place, or why wasn’t the action peer-reviewed, and why didn’t that command have roll-back?)
  • Define action items against all contributing factors.

13 - Lessons Learned:

  • Describe what your team is taking away from this event.
  • What did you learn that will help you in the future to prevent similar events?
  • What unexpected things happened?
  • What process broke down?
  • Lessons learned should correlate directly, if possible, with an action item.

14 - Action items:

  • List of action items with a title, an owner, due date, a priority, and a link to the backlog item created * to follow up.
  • Example: Evaluate shorter timeout for GET API 123, adhorn, July 3rd- 2020, high priority, link to a backlog * item.